Project Description
The project includes addition of sidewalks and crosswalks on Tilden Street from Peirce Mill on the east to Linnean Avenue NW on the west. The work items include removal of the existing pavement markings and concrete sidewalk, pipe culvert installation, stone curb, concrete sidewalk and accessibility ramp construction, signing and pavement markings.
Anticipated Timeline
Advertisement and Award: Fall 2018-Winter 2018/2019
Construction: Spring 2019 – Fall 2019