Project Description
The work on Warren Wagon Road west of Payette Lake is largely complete. A new project, scheduled to start construction in late spring 2020, will start north of East Side Road and end just south of Fischer Creek Bridge. Key Project Elements include:
- Construct Frost-resistant pavement
- Stabilize areas of shallow roadway slides
- Reconstruct sharp curve with standard roadway crown and signs
- Replace old guardrail
- Install culverts to improve drainage
Contractor’s Public Information Office
Crea Construction, Inc.1508 Tammany Creek, Rd.Lewiston, ID 83501Phone: (208) 746-3072Contractor's Public Information Contact
Bryan Peters, Public Information Officer
(208) 503-2032
Anticipated Road Closures
The road is open to public traffic, no further delays are anticipated.
Project Partners
- Valley County
- Federal Highway Administration – Western Federal Lands Highway Division
Newsletters
Anticipated Timeline
- Contract Advertisement & Award – Winter 2019/2020
- Construction – Late Spring/Summer 2020
- Anticipated Completion – Fall 2020
- Project Completed - Fall 2020